Mortlake Power Station Project Gas Pipeline Indigenous Land Use Agreement (ILUA) |
Date: | 27 September 2006 | |
Sub Category: | Indigenous Land Use Agreement (ILUA) (Native Title Act) |
Place: | |
|
State/Country: | Victoria, Australia |
|
| The ILUA area covers land and waters within parts of Allotment 13A- Parish of Laang, 7C- Parish of Narrawaturk and 81C- Parish of Brucknell. All these areas are in Victoria. |
Legal Status: | Registered with the National Native Title Tribunal on the Register of Indigneous Land Use Agreements on 27 September 2006. This is an authorised Area Agreement under the Native Title Act 1993(Cth) | |
Legal Reference: | National Native Title Tibunal No.: VI2005/016 | |
Subject Matter: | | Consultation | Economic Development | | Land Use | Oil and Gas |
Summary Information: | |
This ILUA concerns the establishment of the Mortlake Power Station Gas Project pipeline in Victoria. |
Detailed Information: | |
The Kirrae Whurrong Group agrees to support the doing of the agreed future acts, to take any measure necessary to enable the proponent to obtain a permit and project consents and not to hinder directly or indirectly the grant or exercise of rights resuant to the permit or project consent.
The Kirrae Whurrong Group also agrees that any agreed future acts done within the agreement area are valid and that the Mortlake Power Station Project Gas Pipeline will be established.
If the proponent gives 30 days notice to the Kirrae Whurrong signatories, prior to project approval, that it no longer intends to build the pipeline or that it has decommissioned the pipeline, the agreement may terminate. Further, the agreement may be terminated by agreement in writing by both parties.
| |